Production sites, work centres and routings
Updated:
The master data for production: production sites, work centres with their calendar and capacity, and routings per manufactured item.
Open Production in FiattoIn this article
Production rests on three kinds of master data. You manage Production sites and Work centres under Projects & production → Production master data (/dashboard/productie), and Routings under Production planning → Routings (/dashboard/productie/planning/routings). Approvers make changes; the Production module must be part of your subscription.
Steps
- Click Add production site: name, code, address and the Stock location the site is linked to.
- Click Add work centre for each capacity resource: Type (machine, labour or cell), Capacity (min/day), Efficiency (%), Crew (people or machines), Workdays and whether it is closed on the company's public holidays. For costing, enter Cost per hour (€) and Overhead surcharge (% of labor); the Energy intensity (kWh/hour) feeds the ESG estimate.
- Under Different capacity per period, use Add period to record maintenance, a company shutdown or overtime: minutes per day for that period, 0 = closed.
- On the Routings tab, use Add routing to create an operation plan per manufactured item and Add operation to add its steps: work centre, Setup time (min), Run time (min/unit) or subcontracted to a supplier.
Tips
- A Role (job title) on the work centre makes operations without an assigned employee count as staffing demand for that role.
- Link a Machine in Assets: open work orders on that machine reduce capacity on their due date by the estimated hours.
- A production order uses the item's active routing by default. Without a manufactured item you cannot create a routing: start a bill of materials first.
- The calendar drives capacity in capacity planning and finite day scheduling.
- While something is still missing, Production master data shows the checklist Your first production order: six steps from a production site with a stock warehouse to the first completion, each linking to where you set it up. The block disappears once every step is done.
- Record Quality check points per operation with Add check point: a pass/fail check or a measurement with a limit. These checks appear on every production order with this routing.