Monthly project status report

Updated:

One status report per project per month: green, amber or red on schedule, budget, scope and risk, with commentary, frozen figures and a PDF.

Open Projects in Fiatto
In this article

On the Overview tab of the project dossier (/dashboard/projecten) you create one report per month under Status reporting. You rate schedule, budget, scope and risk as green, amber or red, write a commentary, and Fiatto records the project's figures alongside. Changing it requires write access to projects.

Steps

  1. Open the project; Status reporting with the current month is on Overview.
  2. Rate Schedule, Budget, Scope and Risk and fill in the Commentary for the steering committee. If you leave schedule or risk empty, Fiatto fills in a proposal from the figures on first save; you assess budget and scope yourself.
  3. Choose Save draft. You can still update a draft or discard it with Delete draft.
  4. Choose Finalise once all four ratings are filled in. After that the report can no longer be changed.

Tips

  • The figures are counts and dates only: tasks done and overdue, open and high risks, proposed and approved change orders and the planned end date, no amounts. On finalising, Fiatto freezes them with a fingerprint (sha256).
  • Earlier reports lists the last twelve reports, each downloadable as PDF.
  • A report on a whole programme is made on the programme page, see governing programmes.
  • If an active project previously finalised a report but has not yet done so for the previous month, Project status report missing appears in To do → Actions from the 8th of the month, addressed to the project manager. It disappears as soon as the report is finalised.