Run and complete production orders
Updated:
Release records the material basis; you log time per operation, report (partial) completion with scrap and close the order.
Open Production in FiattoIn this article
Under Projects & production → Production execution (/dashboard/productie/uitvoering) you work through production orders: release, log time, report completion and close. The Open production orders list groups orders by due date (late, today, later) and links to the order page (/dashboard/productie/planning/<id>).
Steps
- Release turns the bill of materials active on the due date into the Required materials pick list and records quantities and source warehouses (Material basis at completion). Nothing is reserved. Download the Work order (PDF) with pick list and QR code if needed.
- Choose More order actions → Start to set the order to In progress. Under Operations (from the routing) you assign employees and log time: with Start and Stop, or as minutes (setup or run) with Log.
- Report complete posts the consumption: components leave stock according to the recorded material basis (backflush) and the finished product is added. For a discrete order you enter the Accepted quantity; the difference from the order quantity is scrap and requires a reason. Choose Report partial quantity to report part while the order continues, or Finish order for the rest.
- Once the order is Done, Close closes it for good; after that no time corrections are possible.
Tips
- Batch/process: when reporting completion, enter the Actual quantities per output; the main product is required.
- Employees with their own personnel record log their own time while the order is released or in progress; approvers can also log for others and add late minutes to a completed order. A clock running longer than 24 hours logs nothing.
- Cost & variance compares actual material and labour with the item's standard cost; Posting follow-up shows the general ledger postings (for approvers and accountants).
- Short of components? By default stock may go temporarily negative; only if "block on shortage" is enabled for your company (off by default, not self-service — contact support) is completion refused. Run MRP purchasing or a stock movement first.
- If Completion stuck appears, choose Recover completion on the order page.
- Energy and batch registration can feed ESG.
- If the order has Quality checks, an open or rejected check blocks reporting completion; a measurement outside the limit counts as a rejection.
- A batch order can also be reported in parts with Report partial quantity and closed with Finish order; rejections with a reason are possible here too.