Capacity planning for production

Updated:

Load per work centre and employee over 8 weeks, with overload advice, proposed orders and opt-in APS-light day scheduling.

Open Production in Fiatto
In this article

Under Projects & production → Production planning, tab Capacity planning (/dashboard/productie/capaciteit), you see the load per work centre and per employee per week against capacity. The horizon is fixed at 8 weeks from this Monday. Capacity comes from the work centre calendar: minutes per day × efficiency × crew over the working days, taking public holidays and exception periods into account (see production sites, work centres and routings).

Steps

  1. Open the Capacity planning tab in production planning.
  2. Read the Work centres and People tables: hours per week; overload turns red. An order without a start date is scheduled backwards from the due date.
  3. If a work centre is overloaded, Work centre overloaded: … appears at the top with the orders loading that week and a recommendation. Carry it out with Start orders today or Plan overtime; if the excess is too large, the advice is to subcontract or add people.
  4. Review Proposed orders (confirmed sales orders for manufactured items not covered by stock and running production) and Plan vs. actuals (completed orders) over the last 90 days. Further adjustments are made on the order itself, see planning a production order.

Tips

  • APS-light — day schedule (finite capacity) is opt-in: an administrator clicks Enable on this page. You get a simulation in due-date order with the list Orders at risk of finishing late.
  • Proposed orders already count in the work centre load and staffing demand, but are not yet production orders.
  • Plan vs. actuals above 110% means the routing standard is too tight, below 90% too generous.
  • This is production capacity — project hours are in project capacity.